Golden Plains Battery Energy Storage System (BESS)

Project Overview

Golden Plains BESS (Battery Energy Storage System) will be a 150MW/600MWh system and construction commenced early 2026. The project is located within Golden Plains Wind Farm – East project area next to the constructed wind farm 220kV substation. The BESS will consist of up to 168 Megapack XL 2.0 battery systems, substation and operational facility.

Golden Plains Energy Storage System logo
Project Owner

TagEnergy

Construction Commencement

February 2026

Equipment Delivery

October 2026

Energisation

Q1 2027

Completion

Estimated 2 years – mid 2027

Battery Technology

168 Tesla Megapack XL 2.0

Installed Capacity

150 MW

Installed Energy

600 MWh

Golden Plains Energy Storage System BESS Map